Project Start Date: Thu 11/16/06
Project Finish Date: Thu 1/17/08
| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 | Preparation | 95.63 days? | Thu 11/16/06 | Thu 3/22/07 | ||
| 2 | Design Dogleg dipole vacuum chamber | 1 day? | Thu 11/16/06 | Thu 11/16/06 | ||
| 3 | Build same | 3 wks | Tue 11/21/06 | Tue 12/12/06 | 2 | |
| 4 | Aquire Spectrometer | 1 day? | Tue 11/21/06 | Tue 11/21/06 | ||
| 5 | Design Spectrometer vacuum chamber | 7 days | Tue 11/21/06 | Mon 12/4/06 | 4 | |
| 6 | Build same | 1 mon | Mon 12/4/06 | Fri 12/29/06 | 5 | |
| 7 | Remaining Optical design of Beamline | 2 wks | Thu 11/16/06 | Thu 11/30/06 | ||
| 8 | Choose Diagnostics | 1 day | Thu 11/30/06 | Wed 12/6/06 | 7 | |
| 9 | Design Beamline Vacuum | 3 days | Wed 12/6/06 | Fri 12/8/06 | 8 | |
| 10 | Aquire BPM buttons | 4 mons | Mon 11/27/06 | Fri 3/9/07 | ||
| 11 | Aquire BPM housings | 6 wks | Tue 11/21/06 | Wed 1/3/07 | ||
| 12 | Assemble new BPMs | 2 wks | Fri 3/9/07 | Thu 3/22/07 | 10,11 | |
| 13 | Aquire OTR crosses | 1 mon | Tue 11/21/06 | Mon 12/18/06 | ||
| 14 | Aquire OTR actuators | 1 mon | Tue 11/21/06 | Mon 12/18/06 | ||
| 15 | Aquire OTR mirror holders | 2 wks | Tue 11/21/06 | Tue 12/5/06 | ||
| 16 | Aquire windows | 14 days | Tue 11/21/06 | Mon 12/11/06 | ||
| 17 | Aquire digital cameras | 1 mon | Tue 11/21/06 | Mon 12/18/06 | ||
| 18 | Aquire camera mounts/firewire, etc | 1 mon | Tue 11/21/06 | Mon 12/18/06 | ||
| 19 | PreAssemble new Crosses | 3 wks | Mon 12/18/06 | Wed 1/10/07 | 13,14,15,16 | |
| 20 | Aquire Beamline Supports | 14 days | Tue 11/21/06 | Mon 12/11/06 | ||
| 21 | Design New Tables | 7 days | Tue 11/21/06 | Fri 12/1/06 | ||
| 22 | Aquire New Tables | 5 wks | Tue 11/21/06 | Tue 12/26/06 | ||
| 23 | Design RF Cavity | 1 day | Thu 11/16/06 | Thu 11/16/06 | ||
| 24 | Build Same | 3 mons | Thu 11/16/06 | Wed 2/7/07 | 23 | |
| 25 | Aquire vacuum components for Tim's Line | 6 wks? | Wed 12/6/06 | Wed 1/17/07 | 7,8 | |
| 26 | Aquire vacuum components for straight line | 6 wks? | Wed 12/6/06 | Wed 1/17/07 | 7,8 | |
| 27 | Installation Phase I | 23 days? | Wed 1/17/07 | Wed 2/14/07 | 3,26,20 | |
| 28 | Break Vacuum | 1 day? | Wed 1/17/07 | Wed 1/17/07 | ||
| 29 | Remove desired components | 3 days | Thu 1/18/07 | Mon 1/22/07 | 28 | |
| 30 | Install Tables | 4 days | Mon 1/22/07 | Fri 1/26/07 | 22,29 | |
| 31 | Modify A0 Beamline | 2 wks? | Mon 1/22/07 | Fri 2/2/07 | 29 | |
| 32 | Install Dogleg Dipole 1 | 1 day? | Fri 2/2/07 | Mon 2/5/07 | 31 | |
| 33 | Install other components | 7 days | Fri 2/2/07 | Mon 2/12/07 | 31 | |
| 34 | Close Vacuum | 2 days | Mon 2/12/07 | Wed 2/14/07 | 32,33 | |
| 35 | Alignment Crew | 7 days | Wed 1/17/07 | Thu 1/25/07 | ||
| 36 | Commission new A0 Beamline | 2 days | Thu 1/25/07 | Mon 1/29/07 | 35 | |
| 37 | Installation Phase II | 32 days? | Thu 3/22/07 | Tue 5/1/07 | 12,25,24,7,8,19,20,22 | |
| 38 | Break Vacuum | 1 day? | Thu 3/22/07 | Thu 3/22/07 | ||
| 39 | Install RF cavity | 3 days | Fri 3/23/07 | Tue 3/27/07 | 38 | |
| 40 | Install components | 14 days | Tue 3/27/07 | Fri 4/13/07 | 39 | |
| 41 | Close vacuum | 3 days | Fri 4/13/07 | Tue 4/17/07 | 40 | |
| 42 | Install Cameras/Electronics | 7 days | Fri 4/13/07 | Mon 4/23/07 | 41SS | |
| 43 | Alignment Crew | 7 days | Mon 4/23/07 | Tue 5/1/07 | 42 | |
| 44 | Commission Tim's Cavity | 2 wks? | Tue 5/1/07 | Mon 5/14/07 | 37 | |
| 45 | Commission new beamline | 7 days | Tue 5/1/07 | Wed 5/9/07 | 37 | |
| 46 | Commission new interlocks | 1 day | Tue 5/1/07 | Wed 5/2/07 | 37 | |
| 47 | Rad Safety Clearance | 1 day? | Wed 5/9/07 | Thu 5/10/07 | 46,37,45 | |
| 48 | Make Measurment | 4 mons | Mon 5/14/07 | Tue 8/21/07 | 47,44 | |
| 49 | Tim Writes Thesis | 6 mons | Tue 8/21/07 | Thu 1/17/08 | 48 | |
| 50 | Tim Graduates | 0 days | Thu 1/17/08 | Thu 1/17/08 | 49 |